Two projects, told start to finish. Employers are left unnamed. For the open-source system I build, see AIEOS.

GitOps at a regulated broker-dealer
#

The problem
#

I set out to bring GitOps to a large broker-dealer. In financial services you don’t get to ship it and see what happens. Before anything moves, someone asks four questions: who approved this, how does it roll back, how many customers can it hurt and, if it goes wrong, how will you prove what happened?

The constraints
#

The architecture and technology review boards had to approve the design. The audit trail had to hold up for a regulator without me in the room to explain it.

What I did
#

I spent six months in front of those boards, answering the four questions with more specificity each round. It was slow. It was also the most useful design review the initiative ever got. By the time the first team deployed to production through the new pipeline, we had a tested rollback procedure and an audit trail a regulator could walk on their own.

Adoption looked great for a quarter. Teams onboarded and the review board was happy. In the second quarter the curve stalled, and nobody on the team noticed because the dashboards were all green. I went and talked to the teams that hadn’t moved. Almost none of their reasons were technical. The blockers were political, and a half-day negotiation with the product owners fixed it. The curve picked back up the next sprint.

The result
#

GitOps went firm-wide. Progressive delivery with Flagger came later and inherited the trust the first approval had earned.

The lesson
#

Fight for the yes early. A yes that takes six months tends to hold, because every objection surfaces while it’s still cheap to fix. And measure adoption. The platform was healthy the whole time the adoption curve was failing.

Six weeks to four days
#

The problem
#

I inherited operational workflows where new teams took six weeks to onboard. The platform team had been adding documentation and the number hadn’t moved. Their theory was that new teams weren’t reading carefully enough.

What I did
#

We didn’t write more docs. New teams were stalling at four handoff points. We collapsed two of them, automated one and put a single owner on the fourth.

The result
#

New teams started shipping in four days. Defect rates dropped and throughput improved.

The lesson
#

Six weeks was a structural problem dressed up as an onboarding problem. Time to first success, from “we’re adopting this” to “we shipped something to production with it,” is the only number I trust for whether onboarding works. Most platform teams have never measured it.

Talk to me
#

If one of these looks like a problem you have, connect with me on LinkedIn.